March 13, 2017
Contacts:
Nancy Shiffler, Michigan Sierra Club, 734-971-1157,
nshiffler@comcast.net
Lea Harper, (419) 450-7042,
wewantcleanwater@gmail.com, www.FWAP.org
Terry Lodge, (419) 205-7084, lodgelaw@yahoo.com
The Sierra Club
and Freshwater Accountability Project, parties to the E.T. Rover gas
mega-pipeline licensing case, have asked the Federal Energy Regulatory
Commission (FERC) to require the company to install turbine instead of reciprocating
engines in each of the planned nine compressor pump stations along the
route.
In a letter to
FERC, the groups cited a commitment to use turbines which appears in the Final
Environmental Impact Statement (“FEIS”) for Rover. A citizen watchdog, who is
also a professional engineer, found the “bait and switch” and brought the
concerns forward for investigation by FERC.
The use of turbines was designated to avoid causing an
irritating “pulsing” vibration to emanate from the compressor stations, which
is admittedly very distracting to nearby residents. The staff of FERC wrote the FEIS, and the
groups maintain that the assurance of turbine use at the compressor statements
is a legally-enforceable condition which cannot be abandoned within the permit
that was subsequently granted by the FERC Commissioners.
“The FERC
Commissioners met and voted on February 2, 2017 that the Environmental Impact
Statement adequately reduces environmental harms, including the pulsing
vibrations from compressors,” said Leatra Harper, intervenor to the case as
Managing Director or Freshwater Accountability Project. “That should have
legally locked in the use of turbines, but instead, the Commissioners approved
reciprocating engines and offered no explanation for the switch.” Besides being noisier, reciprocating engines
are also more polluting because they are less efficient, and are likely less
expensive as well.
Rover has
obtained Ohio Environmental Protection Agency permission to install
reciprocating engines in all nine planned compressor stations. “We believe that
Rover must be held to the FEIS commitment under NEPA regulations, and that only
in the rarest of circumstances (none of which are present here) should any
change to that commitment be allowed,” commented Terry Lodge, attorney for the
FreshWater Accountability Project. “If the FERC decision is not corrected, we
will seek to block construction of any of the compressor stations until this
disagreement is resolved.”
Rover has
already been found in non-compliance with regulations by FERC and was
sanctioned when the company caused the demolition of the historic Stoneman
House in eastern Ohio, which apparently held up FERC approval of the pipeline’s
certificate for months.
A copy of the complaint letter sent to FERC can be found
here:
###
No comments:
Post a Comment